Phase I “Endeavor”​ 500,000 Sq. Ft. Office Building with Labs
Completed 2017, early and under budget 

Phase II “Voyager”​ 750,000 Sq. Ft. Office Building with Labs
Completed 2022​, two months early and ~$80M under budget

Project utilized a Design-Build approach and proactive coordination to enabled a phased design construction and delivery of a new 1.25M sf HQ with seamless indoor-outdoor connection and a pedestrian bridge. Voyager project approvals obtained in less than 6 months. An extensive implementation of biophilic design, including a $30M private outdoor workspace. The design team utilized NVIDIA® Iray® rendering technology to facilitate material selection and optimize daylight and interior quality of light.

Owner: NVIDIA Corporation

Development Manager: Sares Regis

Architect: Gensler

General Contractor: Devcon Construction, Inc.

Photo Credits: Jason O’Rear