Phase I “Endeavor” 500,000 Sq. Ft. Office Building with Labs
Completed 2017, early and under budget
Phase II “Voyager” 750,000 Sq. Ft. Office Building with Labs
Completed 2022, two months early and ~$80M under budget
Project utilized a Design-Build approach and proactive coordination to enabled a phased design construction and delivery of a new 1.25M sf HQ with seamless indoor-outdoor connection and a pedestrian bridge. Voyager project approvals obtained in less than 6 months. An extensive implementation of biophilic design, including a $30M private outdoor workspace. The design team utilized NVIDIA® Iray® rendering technology to facilitate material selection and optimize daylight and interior quality of light.
Owner: NVIDIA Corporation
Development Manager: Sares Regis
Architect: Gensler
General Contractor: Devcon Construction, Inc.
Photo Credits: Jason O’Rear